You Cannot Camp on Your Own Vacant Land in Cochise County

The county's answer is a flat no — camping needs an established use on the parcel. What a temporary use permit actually allows while you build.
The plan is close to universal among people buying rural acreage: get the land cheap, park a travel trailer on it, live there while you build, and let the house happen at whatever pace the budget allows.
The first half of that plan is not permitted in unincorporated Cochise County, and the county's own wording is not ambiguous about it.
Cochise County, on camping on vacant property: "No. There must be a house, or some other established use, on the property in order to camp. This applies to all forms and durations of camping requests."
That last sentence closes the door people usually try next. It is not a question of a weekend versus a season, or a tent versus a trailer. Without an established use on the parcel, camping is not a permitted activity.
What is actually allowed
Two routes exist, and both require a permit rather than merely good intentions:
| Situation | What the county allows |
|---|---|
| There is already a principal use on the parcel, such as a house | You may be eligible to live in an RV for up to six months in a calendar year, with an approved temporary use permit |
| A principal use is being constructed | You may live in an RV during construction, with an approved temporary use permit |
| Nothing on the parcel and nothing being built | Neither camping nor RV occupancy |
| Renting the RV out | Not permitted. "Recreational vehicles may not be rented out." |
The construction route is specifically framed as temporary occupancy of one RV in conjunction with the construction of a permitted principal use, residential or non-residential. One. Not a trailer for you and another for whoever is helping.
The sequence this forces, and why that is not a bad thing
Read together, those rules mean the RV cannot come first. Something has to be under construction before living on site becomes lawful, which means the permit comes before the trailer.
That order is more sensible than it first appears, because it forces the expensive discoveries to happen before you are committed:
- Legal access, before anything — a parcel you cannot lawfully reach cannot be built on or delivered to. See owning land you cannot legally reach.
- Zoning check. The county's interactive map will tell you the district; a Zoning Verification Letter gives you it in writing.
- Septic. A soil and site evaluation, then a design, then a permit — and remember that septic permits expire after two years, so do not pull one three years before you build. Our septic guide covers the process and the composting toilet trap.
- Water. Well or hauled, decided on numbers rather than hope — hauled water versus drilling.
- Building permit, then the temporary use permit for the RV.
- Site work — pad, drive, drainage. Our site prep checklist has the phases.
The people who get into trouble are the ones who do this in reverse: buy, move a trailer on, live there for a year, and then discover the perc test fails, or the access is not legal, or the zoning district will not carry what they intended to build.
Things the RV still needs
An approved temporary use permit is permission to occupy, not a suspension of everything else. In particular:
- Wastewater has to go somewhere legitimate. If you are in the county's Owner-Builder Program you will be required to obtain a septic or alternative waste treatment permit, and an RV holding tank is not a wastewater system.
- Water has to arrive. Hauling to a tank is normal here; sizing it for a trailer plus a build is the part people underestimate.
- Power. A trailer plus tools plus a December week is a real load — see off-grid solar in winter.
- A right-of-way permit may be required if the property is accessed from a county road, and a floodplain use permit if any of it sits in a designated floodplain.
What we could not confirm
- We could not confirm the fee for a temporary use permit, how long review takes, or how long an approval remains valid. The county reviews the application and sends written authorisation approving or denying — ask about duration when you apply, because a build that outlasts the permit is a predictable problem.
- We could not confirm whether a temporary use permit for construction can be renewed or extended, or what happens if the build stalls.
- We could not confirm whether the six-month allowance for an RV alongside an existing house must be continuous or can be split across a calendar year.
- We could not confirm how the county treats a park model, a converted bus, or a tiny house on wheels for these purposes. The county has adopted Appendix Q of the 2018 IRC for tiny homes, which is a building code question rather than an occupancy one, and the two do not obviously line up. Ask before you buy the thing.
- We could not confirm enforcement practice — how the rule is complained about, investigated or acted on. Absence of enforcement is not permission, and it is not a plan.
- Rules change and this is a summary. Development Services is the authority for your parcel.
The short version
You cannot camp on vacant land you own in unincorporated Cochise County — the county's answer is a flat no covering all forms and all durations, because camping requires an established use on the parcel. Living in an RV is allowed in two situations only: alongside an existing principal use such as a house, for up to six months in a calendar year, or while a principal use is under construction. Both need an approved temporary use permit, it is one RV rather than several, and renting it out is not permitted. So the trailer cannot lead — the access, the zoning, the septic and the building permit all come first, and the practical effect is that you find out whether the parcel works before you are living on it.
Sulfur Springs Land Management does the groundwork that has to happen in that window — access, pad, drainage — and doing it in the right order is most of the value.
Gear for this job
Affiliate links — we may earn a commission from purchases at no extra cost to you. We only list gear we would actually put on a job.
- Camco TastePURE 25 ft Potable Water Hose — Drinking-water rated rather than a garden hose. Obvious until the first summer, when a garden hose starts tasting like a garden hose.
- RomoTech 325 Gallon Polyethylene Storage Tank with Legs — Legs give you gravity feed without building a stand, which is what you want for a trailer rather than a house.
- Yaktek Levetator Water Tank Level Gauge — Hauled water runs out on a schedule you set. Knowing the number beats climbing up to look.
- SHURFLO Revolution 12V Fresh Water Pump, 3.0 GPM — Runs off the trailer's 12 volt system, which matters when the house circuit does not exist yet.
Ready to Develop Your Land?
Sulfur Springs Land Management specializes in land clearing, grading, solar system consultation, and comprehensive off-grid property development. Let's turn your land into your dream off-grid property.
Contact SSLM TodayMore from the Blog
Getting Power to Rural Land: The Estimate Is Not a Price
SSVEC can bill for unanticipated costs up to six months after the work, and obtaining the easements is your job. What a line extension involves.
Rural LivingSplitting a Parcel: The County Will Record a Bad Split
A minor land division permit does not split your land — the deed does. And a split with no legal access can still be recorded if the deeds say so.
Rural LivingRunning a Business From Rural Land: The 25% Rule
Cochise County caps a home occupation at 25% of the residence floor area — even in a detached shop — and prohibits outdoor storage entirely.
Rural LivingSecond Dwellings: What Cochise County Allows on One Parcel
An ADU needs planning approval before any building permit, the owner must live on site, and an RV never qualifies. Park models do, with conditions.
Rural LivingWhat You Can Build Without a Permit in Cochise County
A 200 sq ft shed is exempt until you run power to it. The county's exemption list, the $1,000 threshold, and the fence rule that catches people.
Rural LivingFloodplain Rules Reach Further Than the Flood Map
A floodplain use permit covers grading and fencing, not just building — and watercourse setbacks of 50 to 300 feet apply to every structure.
Rural LivingThe Owner-Builder Option That Costs You the Certificate
Cochise County's no-inspection owner-builder path is cheaper and never gets a Certificate of Occupancy. What that means for lenders, insurers and buyers.
Rural LivingOpen Range: In Arizona You Fence Cattle Out, Not In
Arizona law bars recovery for livestock trespass unless your land sits inside a statutory lawful fence — and the statute specifies the wire spacing.
Rural LivingRural Internet: The FCC Map Shows Claims, Not Service
The national broadband map reports what providers say they offer at your parcel. How to check it, and the two challenges you can file when it is wrong.
Rural LivingDefensible Space in Cochise County Starts at the Driveway
Arizona's home ignition zones run 0-5, 5-30 and 30-100 feet. But an engine needs 12 feet of width and 15 of clearance to reach you in the first place.
Rural LivingA Composting Toilet Does Not Get You Out of a Septic System
Arizona excludes the kitchen sink from gray water, so a composting toilet still needs septic. The Type 4 permit, percolation testing and the reserve area.
Rural LivingOwning Arizona Land You Cannot Legally Reach
A dirt track to your parcel is not legal access. What Arizona's private way of necessity actually is, where easements are recorded, and what to check first.
IndustrySulfur Springs Valley: Two Water Districts, Not One
The valley is not one groundwater basin but two — Willcox in the north, Douglas in the south — with different rules. What every landowner should know.
IndustryHauled Water vs Drilling a Well: The Real Numbers
What a well really costs at 200-350 ft static water level in Sulfur Springs Valley, what hauled water costs per year, and where the break-even sits.
Rural LivingOff-Grid Solar in Winter: Sizing for Cochise County's Worst Days
Cochise County winter drops you to 4-5 peak sun hours. How to size batteries, autonomy days, inverters and charge controllers for the worst week.
Rural LivingB-Grade vs A-Grade Solar Panels: Is the Discount Worth It?
What the A/B grade distinction actually describes, why B-grade panels cost less, and when the cosmetic-versus-electrical trade-off is worth taking.
Rural LivingGoat Kids Hide: The Chihuahua Rule for Off-Grid Livestock
Newborn goat kids hide by instinct and vanish on cleared desert ground. A simple sizing rule for clearing that keeps them findable.
Land PreparationOff-Grid Site Prep Checklist: Pad, Access, Drainage, Utilities
A phased checklist for turning raw Cochise County land into a buildable site: survey, building pad, access road, drainage, utilities and septic.
Off-Grid LivingOff-Grid Solar in Arizona: How Many Panels Do You Need?
How many panels an off-grid Arizona property actually needs, what a full system costs in 2026, and the three tiers most Cochise County builds fall into.
Land ClearingLand Clearing in Cochise County: What to Know Before You Start
What land clearing costs in Cochise County, what you may and may not remove under Arizona rules, and which equipment suits mesquite and creosote.
Off-Grid LivingComplete Guide to Off-Grid Water Systems in Rural Arizona
Wells, hauled water, storage and pressure systems for a rural Cochise County property — how the pieces fit and what each one demands of you.